What does the term 'fast-track construction' refer to?

Study for the South Carolina Property Management License Exam. Access flashcards and multiple-choice questions with comprehensive hints and explanations. Prepare effectively for your certification!

The term 'fast-track construction' refers to the practice of beginning work on a project before the final plans and specifications are fully completed. This approach allows construction to proceed at an accelerated pace, often to meet tight deadlines or to deliver projects more quickly. By overlapping the design and construction phases, fast-tracking can lead to reduced construction times and can also create efficiencies in project delivery.

Starting the construction before all the plans are finalized means that some parts of the project can be built while other aspects are still being designed, which can be particularly beneficial in dynamic projects where time is of the essence. This method requires careful coordination and communication among all stakeholders to ensure that the work being done is aligned with the evolving plans.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy